More than 30 years of experience in different position and department in “Azar-Ab Industries Co.” Iran; a leading company that is active in design, procurement, manufacturing and installation of almost whole equipment and disciplines on Chemical, Petrochemical, Petroleum and Energy Industries.

Areas of specialization includes pressure vessels, heat exchangers, air cool­ers, boilers(different type such as power plant ,HRSG ,Industrial , Utility, Package Boilers),atmospheric flat bottomed-tanks, towers piping systems, hydro power plant equipment.

Expert with comprehensive work study , planning and preparation of work related to fixed and floating roof tanks ,pressure vessel and heat exchanger, all kind of boilers and so on.

Experienced in detail engineering, including preparation of detailed fabrication drawings and specification for material supply, fabrication, welding, erection and inspection, preparation of technical bid tab­ulations, negotiations with Vendors, Vendor follow-up and document review, as well as fabrication control and inspection. Furthermore, experienced in workshop management, pro­ject planning, control and site management for different projects.

Familiar with international standards the same as ASME

- Familiar with the processes of manufacturing and planning various products such as pressure vessels and heat exchangers, storage tanks and refueling towers, as well as a variety of power and utility boilers including combined cycle boilers and heat recovery. This included the presence in the project in the project engineering departments as well as the management of related projects in EPC form. Planning and monitoring of programs in the MSP platform and P6, preparing related reports and applying them to meetings with employers and contractors Domestic and foreign. Developing their update plans during the course of the project, and eventually preparing complaints and changes to the project and so on.


کد معرف برای ثبت نام دیگران: 17271
سابقه فعالیت ها:

FUNCTIONS AND MAIN RESPONSIBILITIES WITHIN Azarab co.

  • 2018 - To date AZAR-AB IND.CO ARAK/IRAN

As Project Manager
2 x 227 T/H Industrial boiler + 3unit fresh air firing HRSG boiler for Isfahan refinery project (EPC). Project value approx. 35 M €.

It was about 4500 MT mechanical and piping work that was design and manufacture in house and transport to the site. Also procurement of various equipment from Abroad such as pumps, burner, forced draft fans, shut off valves, MOV, steam turbine and others.

  • 2017 - 2018 AZAR-AB IND.CO ARAK/IRAN

As Project Manager
3 x 140 T/H Utility boiler Ghachsaran petrochemical plant project (EPC). Project value approx. 15 M €.

It was about 3000 MT mechanical and piping work that was design and manufacture in house and transport to the site. Also procurement of various equipment from Abroad such as pumps, burner, forced draft fans, shut off valves, MOV, steam turbine and others.

 

  • 2013 – 2017AZAR-AB IND.CO ARAK/IRAN

AS EXECUTIVE MANAGER OF HYDRO AND WIND POWERPLANT

Based on Iran’s developing policies and localizing the basic industry technology, departments’ goals are de fined in forms of GC and EPC.  Based on our 20 years of experiences from abroad training courses and using our unique equipment, the department and company has capabilities in making power plant precise parts, planning, finance and industrial consultant commerce, making engineering, erection, commissioning and project management in manufacturing hydro power plants, Francis, Kaplan and butterfly valves.

Based on its policy, Azar-Ab has done the engineering construction or left the manufacturing of karun1, Karun2, Karun3, Karun4 or Masjed Suleiman, Karkheh power plant and factories equipment to other regional companies and by distributing the work among the regional companies has performed a significant role.

 

  • 2010 – 2013 AZAR-AB IND.CO ARAK/IRAN

          As Project Manager / Site Manager

         6x180 T/H industrial boilers for South Pars Gas Field Phase no.19 (EPC)

  • 2007 – 2010AZAR-AB IND.CO ARAK/IRAN

          As Project Manager / Site Manager

          4x160 T/H industrial boiler for Karg Island (NGL PLANT) (EPC)

  • 2004 – 2007AZAR-AB IND.CO ARAK/IRAN

          As Project Manager / Site Manager

          2x227 T/H industrial boiler for Arak Refinery project (EPC)

 

  • 2003 – 2004AZAR-AB IND.CO ARAK/IRAN

          As Project Planning and Management/ Site Manager

          Oil storage plant in Chabahar  (EPC)

It was a project with wide range of different kinds of atmospheric  storage tank with various size and services as Gas Oil, APG, ATK that were Fixed roof tank, Tanks with floating roof, Tank with Floating Ceiling and Fixed Ceiling (EFRT), Floating roof and fixed roof (IFRT) tank double deck tanks.

  • 2001– 2003Thyssen croup concern co. /Germany

          As Project Planning and Management novitiate

Passing a three-month German-language course in Dortmund and then a 12-month internship at Krupp in Wadern. About ten seminars on quality management and project management are held.

  • 1998 – 2001AZAR-AB IND.CO ARAK/IRAN

As Operation-Executive Officer for design, purchase, installation and operation of new product. (Finned Tube Production line)

Because AzarAb Company was planning to add a scoop to the design, construction, and operation of combined cycle boilers, there was no Finn Tube production in factory until then. I was considered to be the director of the project, which during the two years this line Success has just started.

  • 1995 – 1998AZAR-AB IND.CO ARAK/IRAN

          As Production Planning and control Manager

The management of this sector included the implementation and control of engineering, the construction in workshops, and the monitoring of their implementation, and finally the preparation of daily, weekly monthly management reports both internally and externally.

 

 

  • 1990– 1995AZAR-AB IND.CO ARAK/IRAN

As chief of technology and method department

(Boiler and pressure vessel division)

The responsibility for this section includes monitoring the preparation of documents based on data plans and presenting the workshop's policy for doing the right thing in accordance with the standards.

 

  • 1988– 1990AZAR-AB IND.CO ARAK/IRAN

As chief of technology and method department

As an industrial engineering expert, this section focuses on assessing work and time, optimizing work processes and standardizing work units.


نوع عضویت در باشگاه مدیران ایران: عادی

ارزهای دیجیتال

اطلاعات بیشتر مانند رزومه یا ارسال پیام خصوصی، فقط برای اعضای طلایی قابل مشاهده است.

همین الان طلایی شوید!
+